Tech Browser Topics Essential XL FireKing PDF Library Garda Autobank XLViP
 
Easy 120
Specs
Installation
Operation
Theory
Delay Settings
Wiring Service
Main Board Service
Front Panel Service
Power Service
Vending System Service
Door Service
Manual Drop Service
Parts

Easy 120V / 120A
Specs
Installation
Operation
Theory
Programming
Wiring Service
Main Board Service
Front Panel Service
Power Service
Vending System Service
Validated Drop Service
Manual Drop Service
Door Service
Parts

Smart Series
Common Rules
Audit
Manage Users
Open Door
Vending
Drops
Reports
Clock Setup
Door Setup
Vend Setup
Validator Setup
Location Setup
Troubleshooting
Keypad Replacement
Parts List
McGunn Easy 120V/120A Installation

Space Requirements

Space must be provided for mounting the safe, plus required clearance for access. A minimum gap of one inch must be provided on both sides and four inches at the rear of the safe. Clearance must be provided so that the safe door is allowed to swing open at least 90°.
• 1 Inch Side Clearance
• 4 Inches Rear Clearance
• 90° Door Swing Clearance
• Body Height Clearance

Power Requirements

A standard NEMA 15A 115VAC grounded outlet must be provided within 6 feet of the hinge side of the safe. The unit may share its AC circuit with other point of sale electronic equipment, but must not be on the same circuit as rotating machinery such as a cooler or other refrigeration equipment.
• Standard 115VAC Grounded Outlet
• No Rotating or Heavy Loads on AC Circuit
• Outlet Within Six Feet of Hinge Side.

Remove Safe from Pallet

The safe is shipped with the outer door locked in the open position with rubber bumpers preventing accidental door closure.
1. Remove wrapping material from the safe.
2. Remove the contents of the safe.
3. Unbolt the safe from the pallet.

Verify Operation

1. Locate the power supply unit packaged inside the unit. Unwrap the power supply.
2. Plug the power supply cable into the power supply jack at the rear of the safe.
3. Plug the standard grounded power plug into a standard 115 VAC outlet.
4. Wait for the display to stabilize (about 10 seconds).
5. Use the OPENING OUTER DOOR procedure to unlock the outer door.
6. Use the VENDING TUBES procedure to operate one column’s vend knob as if a tube were present.
7. Using the VALIDATED DROP procedure verify each validator accepts and counts money.
8. These steps verify operation of critical Easy120V features.
If the door or vending system cannot be operated contact McGunn Technical Support immediately and in any event prior to bolting the safe down (1-800-452-4655).

Safe Installation

1. Obtain the anchor wedge kit from inside the safe and set aside.
2. Obtain the footprint template (shipped inside the safe).
3. Using a pencil, mark the mounting hole locations on the floor.
4. Drill four 1/2 inch holes to a depth of 3 inches. The holes must be clean. Use a vacuum to clean the holes. Do not use water to clean the holes.
5. Position the safe so that the bolt-holes align with the holes drilled in the floor. While doing so, feed the power supply cable and alarm cable through cabinet openings (if applicable) for routing access.
6. Drive each anchor wedge in until 1/4 inch to 1 inch of the top protrude through the floor of the safe.
7. Slide the washers down over each anchor wedge.
8. Put the nuts on each anchor wedge by hand until finger tight. Turn approximately three to four full turns by wrench to complete the tightening.


Anchor Wedge